Creekside Entrance Sign Update

Today a few Creekside Board Members met with Alex from Future Forms at the corner of 72nd St E. and 49th Ave to discuss the exact positioning of the Creekside Entrance Sign. A group consensus was reached on placement and Alex stated an informal completion time of 6 to 8 weeks.

Future Forms was selected to produce the sign which will look similar in appearance to the Lakeside and Lakeside II entrance walls, but slightly smaller at 4 feet tall. It will be mounted atop a 1 foot landscaped berm. The approved estimated cost was under $5,000. The sign will not initially be illuminated. The Creekwood Master Board requested AMI to procure at least 3 bids for running new electrical lines as well as solar lighting options. To date, AMI has provided only 1 bid to run news lines with an estimate of nearly $5,000. However, the decision was made to move forward on installation of the new wall and continue to pursue further electrical bids including solar.